Adapting Protection to Island Mode Operation of Microgrids

Oct. 2, 2017
The challenges of protection coordination for island mode operation of microgrids vary per the grid topology and the generation sources such as photovoltaics, reciprocating diesel-driven generators, turbine-driven gensets, wind, batteries, or others. In this week’s Industry Perspectives, Scott Manson, of Schweitzer Engineering Laboratories, explores some of these challenges.

In this week’s Industry PerspectivesScott Manson, of Schweitzer Engineering Laboratories (SEL), explores some of the challenges of protection coordination for island mode operation of microgrids. 

The challenges of protection coordination for island mode operation of microgrids vary per the grid topology and the generation sources such as photovoltaics, reciprocating diesel-driven generators, turbine-driven gensets, wind, batteries, or others.

Scott Manson, SEL Engineering Services technology director at Schweitzer Engineering Laboratories

Consider a typical microgrid like the one shown in Figure 1 below. The system includes a battery capable of producing 145 A at 4 kV (1 MVA), a utility point of interconnect (POI), and a distributed radial load through a community.

Requests normally come in the form of statements or queries such as:

  • “We can’t find a way to get the relay coordination to work.”
  • “We have a safety problem.”
  • “These batteries don’t have sufficient fault current.”
  • “How do we achieve contractual compliance without blacking out our grid?”
  • “Our load grew since we sized our battery—now what?”

The design answers these typical concerns. Notice that there are smart relays at the utility POI, at the reclosers located throughout the distributed radial 4 kV community loads, and adjacent to the battery. The following three-step scenario illustrates how the system works. In Step 1, the utility has an upstream fault and the microgrid islands. In Step 2, the microgrid is island mode has too much load for the battery to carry. In Step 3, a fault occurs on the microgrid in island mode.

Figure 1: Typical Microgrid Protection Challenge. Courtesy of SEL

Step 1. Microgrid islanding starts with a fault, low-frequency event, or low-voltage event on the utility system. The smart POI relay detects this phenomenon and opens the interconnecting device, usually a recloser, circuit breaker, or something similar.

Most utility interconnect contracts contain frequency and voltage ride-through requirements, similar to IEEE 1547, as shown by the POI trip line in Figure 2. As shown by the red line, the challenge for conventional underfrequency elements is that the frequency continues to fall and the distributed energy resources (DERs) trip offline before the POI opens. An 81RF element that incorporates frequency, rate-of-change of frequency, time, and voltage supervision elements will trip early in anticipation of opening the POI at exactly the contractual boundary. The dashed green line shows a typical seamless transition with the 81RF element in use.

Figure 2: IEEE 1547-Compliant POI Isolation.  Courtesy of SEL

Step 2. Once the POI opens, the battery cannot supply all of the load and keep the frequency and voltage at nominal. This is solved by the POI relay sending a load shed trip command to one or more remote smart feeder relays in the distribution system. This can be sent via either Ethernet or serial communications using copper, radio, or fiber-optic media. Proper cybersecurity measures and deterministic operational technology (OT) communications methods must be used.

Step 3. A fault occurs, as shown in Figure 1, between Loads 1 and 2. When the fault occurs, the inverter at the battery expels full rated current and no more. Inverters cannot put out 10 times the rated current like a synchronous generator can. As a result, the fault current is so close to the load current that the relays have difficulty discriminating between them. The use of traditional time-overcurrent methods in this case usually will not work.

Without smart relays, the battery-backed inverter would invariably drop its voltage, run its current to the limit, and trip offline.

Without smart relays, the battery-backed inverter would invariably drop its voltage, run its current to the limit, and trip offline. The relays upstream of the fault would see current while those downstream would not. No single device would have the information needed to properly identify the fault; however, all the devices together (inverter, DER relay, and feeder relays) do have the information required to determine the fault location. Therefore, the solution is to have smart relays that communicate with millisecond-fast communications methods.

The communications and relay decisions occur within a few power system cycles (~30 ms). Included in this time is the ultra-fast hardwired signals between the relay and the battery inverter. Because it all happens so fast, it looks like a “no-blink” power system to users and owners.

Scott Manson is the SEL Engineering Services technology director at Schweitzer Engineering Laboratories

About the Author

Guest Post

In the Race to 100% Renewable Energy, Islands Will Win — With the Right Grid Improvements

March 18, 2024
Looked at individually, islands are often overlooked as unimportant players on the global economic stage. Smaller geographies, smaller communities, fewer resources, and often ...

Grid Beyond Wp Cover 2023 01 06 12 24 33

Global Energy Trends 2023

Over 2021-22, environmental, macro-economic, and geopolitical shocks have put the global energy transition under pressure.