Puerto Rico Approves Utility Plan with Microgrid Mandate

Sept. 8, 2020
After two years of debate and planning, Puerto Rico’s utility finally appears positioned to re-create its electric grid with microgrids and renewable energy, mandated in a new IRP order.

After two years of debate and planning, Puerto Rico finally appears positioned to re-create its electric grid with microgrids and renewable energy, mandated in a new utility integrated resource plan (IRP).

California-based BoxPower is among several  private companies supplying microgrids in Puerto Rico. Photo courtesy of BoxPower

The mandate came from the Puerto Rico Energy Bureau, the island’s chief energy regulator, in late August. Utility IRPs are guiding documents produced by US utilities to determine the least-cost way to manage gaps between existing resources and future needs. PREPA has been working on this version of its IRP since March 2018.

Microgrids became a big part of island reconstruction after its entire grid failed from the onslaught of Hurricane Maria in September 2017. But much of the microgrid development has been piecemeal, done by private, federal or non-profit sources to help schools, hospitals, businesses and remote communities.

Now, however, the bureau has ruled that microgrids must be a central part of the grid planning by the island’s utility, the Puerto Rico Electric Power Authority’s (PREPA).

The bureau ordered PREPA to “directly incorporate promotion of microgrid resources into all of its transmission, distribution, and resource planning,” noting that microgrids “form a critical part of the resiliency solutions envisioned” for Puerto Rico.

Renewables central to IRP

The regulators added that the mandate “includes facilitating timely and non-discriminatory access for all DG (distributed generation) and microgrid facilities to interconnect with PREPA’s grid.”

The order also gives renewable energy a central role and requires that the utility equally weigh a range of renewable technologies. The utility will seek power purchase and operating agreements through competitive requests for proposals (RFPs).

“They’re seeking aggressive RFPs for renewable penetration and they’re agnostic as to which technology,” said Agustín Carbó, senior manager for microgrids at the Environmental Defense Fund, which participated in the proceeding. “There are different options for renewables that need to be considered on equal footing, such as a hydro, solar-plus-storage, wind, off-shore wind. So there is a variety in the mix.”

The competitive solicitations are meant to help the island meet a government goal of 40% renewables by 2025 and 100% by 2050. Renewables now make up only about 2% of its electric supply.

The bureau also requires that the utility issue solicitations for battery energy storage to help integrate renewables and meet peak load requirements. Scenario models indicate Puerto Rico will need to seek somewhere between 2,580-5,200 MW of solar photovoltaics by 2025 and 1,360-1,720 MW of battery energy storage.

PREPA will conduct the auctions with oversight from the bureau. The utility has 60 days to produce a plan for the solicitations.

It’s unclear how robust the bidding will be in light of PREPA’s bankruptcy status and the overall unsteadiness of the COVID-19 economy.

Incentivizing bidders

“It’s a tough market with a tough economy. With everything that’s happening in the world, it definitely could be a challenge. But we’ll see,” said Carbó.

Given the economic challenges, the bureau instructed PREPA to take action to incentivize bidders to offer lower prices, such as finding ways to minimize counterparty risk. This could include staging the RFP processes to avoid locking in higher prices early, if later-stage RFPs are likely to bring in lower bid prices.

PREPA must evaluate the bids based on at least the following criteria: 

  • Cost for energy and capacity
  • Recognition of T&D losses
  • Resilience benefits 
  • Timeline
  • Technical superiority of location for interconnection
  • Nearness to load
  • Locational diversity around the island in proportion to load
Yes to VPPs in Puerto Rico

Aggregations and virtual power plants are “explicitly allowed” to bid, under the order.

In fact, virtual power plants and aggregations come out as winner in the plan

For example, distributed energy resources will be able to compete head to head with utility scale resources for PPOAs, the bureau said, noting that it agrees with Sunrun and others that VPPs can offer capacity to the grid in the form of solar plus storage. 

The order also calls for the utility to create internal systems as well as external programs, offerings, or solicitations to engage demand response aggregators in ways that serve all customer classes.

EDF had pushed for VPPs and aggregations in the plan, expressing concern that despite the growth in customer-sited solar and batteries, PREPA does not offer  any incentives or a procurement process for VPPs.

No to minigrid plan

In an earlier draft of its IRP, PREPA had proposed dividing the island into eight minigrids, but the bureau rejected the $5.9 billion plan. In North America, a minigrid is defined as a large and complex microgrid, in this case cited to support clusters of critical transmission and distribution voltage loads, downstream of distribution and transmission vulnerabilities. 

The utility did not make the case that minigrids are less expensive than alternatives; nor did it fully incorporate microgrids and other distributed resilience measures into the minigrids, the bureau said.

However, the bureau still wants to explore the concept and plans to open a minigrid proceeding in the fall. The bureau is considering one or two minigrid test sites, particularly the San Juan/Bayamon region because of the region’s load density.

The 332 page IRP decision also covers a wide range of other planning issues for the utility, among them new, upgraded and retiring generation, grid hardening, LNG infrastructure, peaking resources, energy efficiency and demand response.

The bureau decision can be found here.

Track news about micorgrids in Puerto Rico. Subscribe to the free Microgrid Knowledge newsletter.  

About the Author

Elisa Wood | Editor-in-Chief

Elisa Wood is an award-winning writer and editor who specializes in the energy industry. She is chief editor and co-founder of Microgrid Knowledge and serves as co-host of the publication’s popular conference series. She also co-founded RealEnergyWriters.com, where she continues to lead a team of energy writers who produce content for energy companies and advocacy organizations.

She has been writing about energy for more than two decades and is published widely. Her work can be found in prominent energy business journals as well as mainstream publications. She has been quoted by NPR, the Wall Street Journal and other notable media outlets.

“For an especially readable voice in the industry, the most consistent interpreter across these years has been the energy journalist Elisa Wood, whose Microgrid Knowledge (and conference) has aggregated more stories better than any other feed of its time,” wrote Malcolm McCullough, in the book, Downtime on the Microgrid, published by MIT Press in 2020.

Twitter: @ElisaWood

LinkedIn: Elisa Wood

Facebook:  Microgrids

Related Content

Brandon Olafsson / Shutterstock.com

Department of Energy Spending Up to $200M Connecting Remote Microgrids

March 15, 2024
The U.S. Department of Energy is currently accepting proposals for transmission projects that would connect remote and isolated microgrids to each other or to existing transmission...
U.S. Army photo by Scott Darling, Fort Cavazos Public Affairs)

U.S. Army Improves Resilience at Fort Cavazos with New Microgrid

March 14, 2024
U.S. Army Garrison-Fort Cavazos, formerly known as Fort Hood, will use the microgrid to power critical services and infrastructure during outages and to reduce energy costs during...

Reducing Costs and Uncertainty in Microgrid Deployment By Employing An Integrated Solution

March 15, 2024
This white paper - the second in a series - explores the Model Predictive Controller (MPC) approach to Microgrid and EV infrastructure operation.

Malaysian Semiconductor Maker Secures Critical Power with Rolls-Royce mtu Powerpacks On-Site

March 13, 2024
X-FAB Sarawak, the Malaysian division of worldwide foundry group X-FAB, will utilize the four mtu Kinetic Powerpacks at its site in Kuching, Sarawak, Malaysia. The company manufactures...

Only through Standardization Can Microgrids Accelerate the Energy Transition

Jan. 18, 2024
Jana Gerber, North America microgrid president at Schneider Electric discusses how standardizing microgrids will accelerate the energy transition.

Get the full report.
Get the full report.
Get the full report.
Get the full report.
Get the full report.

How Utilities Can Be Microgrid Leaders

PXiSE Energy Solutions explores how microgrids can help utilities leverage diverse DER to better serve their customers and reposition themselves in the energy supply value chain...