Puerto Rico Approves Utility Plan with Microgrid Mandate

Share Button

After two years of debate and planning, Puerto Rico finally appears positioned to re-create its electric grid with microgrids and renewable energy, mandated in a new utility integrated resource plan (IRP).

Puerto Rico

California-based BoxPower is among several  private companies supplying microgrids in Puerto Rico. Photo courtesy of BoxPower

The mandate came from the Puerto Rico Energy Bureau, the island’s chief energy regulator, in late August. Utility IRPs are guiding documents produced by US utilities to determine the least-cost way to manage gaps between existing resources and future needs. PREPA has been working on this version of its IRP since March 2018.

Microgrids became a big part of island reconstruction after its entire grid failed from the onslaught of Hurricane Maria in September 2017. But much of the microgrid development has been piecemeal, done by private, federal or non-profit sources to help schools, hospitals, businesses and remote communities.

Now, however, the bureau has ruled that microgrids must be a central part of the grid planning by the island’s utility, the Puerto Rico Electric Power Authority’s (PREPA).

The bureau ordered PREPA to “directly incorporate promotion of microgrid resources into all of its transmission, distribution, and resource planning,” noting that microgrids “form a critical part of the resiliency solutions envisioned” for Puerto Rico.

Renewables central to IRP

The regulators added that the mandate “includes facilitating timely and non-discriminatory access for all DG (distributed generation) and microgrid facilities to interconnect with PREPA’s grid.”

The order also gives renewable energy a central role and requires that the utility equally weigh a range of renewable technologies. The utility will seek power purchase and operating agreements through competitive requests for proposals (RFPs).

“They’re seeking aggressive RFPs for renewable penetration and they’re agnostic as to which technology,” said Agustín Carbó, senior manager for microgrids at the Environmental Defense Fund, which participated in the proceeding. “There are different options for renewables that need to be considered on equal footing, such as a hydro, solar-plus-storage, wind, off-shore wind. So there is a variety in the mix.”

The competitive solicitations are meant to help the island meet a government goal of 40% renewables by 2025 and 100% by 2050. Renewables now make up only about 2% of its electric supply.

The bureau also requires that the utility issue solicitations for battery energy storage to help integrate renewables and meet peak load requirements. Scenario models indicate Puerto Rico will need to seek somewhere between 2,580-5,200 MW of solar photovoltaics by 2025 and 1,360-1,720 MW of battery energy storage.

PREPA will conduct the auctions with oversight from the bureau. The utility has 60 days to produce a plan for the solicitations.

It’s unclear how robust the bidding will be in light of PREPA’s bankruptcy status and the overall unsteadiness of the COVID-19 economy.

Free Resource from Microgrid Knowledge Library

Microgrid Business Models and Value Chains
The new energy industry is working to categorize the various types of microgrids and business models. The primary goal is to minimize microgrid system cost and funding. To learn more about microgrid business modes and value chains download this white paper.
We always respect your privacy and we never sell or rent our list to third parties. By downloading this White Paper you are agreeing to our terms of service. You can opt out at any time.

Get this PDF emailed to you.

Incentivizing bidders

“It’s a tough market with a tough economy. With everything that’s happening in the world, it definitely could be a challenge. But we’ll see,” said Carbó.

Given the economic challenges, the bureau instructed PREPA to take action to incentivize bidders to offer lower prices, such as finding ways to minimize counterparty risk. This could include staging the RFP processes to avoid locking in higher prices early, if later-stage RFPs are likely to bring in lower bid prices.

PREPA must evaluate the bids based on at least the following criteria: 

  • Cost for energy and capacity
  • Recognition of T&D losses
  • Resilience benefits 
  • Timeline
  • Technical superiority of location for interconnection
  • Nearness to load
  • Locational diversity around the island in proportion to load
Yes to VPPs in Puerto Rico

Aggregations and virtual power plants are “explicitly allowed” to bid, under the order.

In fact, virtual power plants and aggregations come out as winner in the plan

For example, distributed energy resources will be able to compete head to head with utility scale resources for PPOAs, the bureau said, noting that it agrees with Sunrun and others that VPPs can offer capacity to the grid in the form of solar plus storage. 

The order also calls for the utility to create internal systems as well as external programs, offerings, or solicitations to engage demand response aggregators in ways that serve all customer classes.

EDF had pushed for VPPs and aggregations in the plan, expressing concern that despite the growth in customer-sited solar and batteries, PREPA does not offer  any incentives or a procurement process for VPPs.

microgrids

The Unite for Puerto Rico Washington Rally in Washington DC protests power outages following Hurricane Maria.  By Rena Schild/Shutterstock.com

No to minigrid plan

In an earlier draft of its IRP, PREPA had proposed dividing the island into eight minigrids, but the bureau rejected the $5.9 billion plan. In North America, a minigrid is defined as a large and complex microgrid, in this case cited to support clusters of critical transmission and distribution voltage loads, downstream of distribution and transmission vulnerabilities. 

The utility did not make the case that minigrids are less expensive than alternatives; nor did it fully incorporate microgrids and other distributed resilience measures into the minigrids, the bureau said.

However, the bureau still wants to explore the concept and plans to open a minigrid proceeding in the fall. The bureau is considering one or two minigrid test sites, particularly the San Juan/Bayamon region because of the region’s load density.

The 332 page IRP decision also covers a wide range of other planning issues for the utility, among them new, upgraded and retiring generation, grid hardening, LNG infrastructure, peaking resources, energy efficiency and demand response.

The bureau decision can be found here.

Track news about micorgrids in Puerto Rico. Subscribe to the free Microgrid Knowledge newsletter.  

Share Button

Sign up for our newsletter and get the latest microgrid news and analysis.
Elisa Wood About Elisa Wood

Elisa Wood is the chief editor of MicrogridKnowledge.com. She has been writing about energy for more than two decades for top industry publications. Her work also has been picked up by CNN, the New York Times, Reuters, the Wall Street Journal Online and the Washington Post.

Comments

  1. In the text above, battery capacity is shown in MW instead of MWH, Megwatt Hours. If the numbers are right, with only the units wrong, then the batteries will only support the system for about half an hour. Flow batteries or fuel cells are less expensive at moderate power for a long time, but they are only beginning to see wide usage.

    • You do realize with a battery, you can “say” it is a 1MWh battery, but if the output inverter is not being called to generate energy there is NO time unit on the battery unless the power stored in the battery is being switched out into the grid. Then it is completely dependent on the inverter(s) itself. IF it is a 100KW inverter, it can supply energy to the grid at 100kWh for about 10 hours, actually with Li Ion it is usually designed for 80% DoD so you would only get 100kWh for 8 hours. This so called 100kW/1MWh energy system has no “energy” when not running to generate into the grid.

  2. “The utility will seek power purchase and operating agreements through competitive requests for proposals (RFPs).”

    It might be a better overall ‘fix’ if a structured micro-grid concept that could be scaled for different needs around the Island and send out bids to (EPC) Engineering, Procurement, and Construction companies that can do both solar PV and wind generation.

    ““There are different options for renewables that need to be considered on equal footing, such as a hydro, solar-plus-storage, wind, off-shore wind. So there is a variety in the mix.””

    The hydro in Puerto Rico is nominal and some small hydro generation facilities need repairs. There’s only an aggregate of something like 2% of hydro generation on the island. IF every resident on the Island had 4.5kWp solar PV and a 25kWh battery, the residential sector could take care of their daily energy needs for around $25 billion dollars for every home on PR. I’ve seen some cost analysis of $14 Billion to around $20 billion dollars to fix the grid and harden the grid. Around $18,000 per household for energy sufficiency.

Leave a Comment

*